MCQs On Project Mangement
1. Which of the following is not a project management goal?
Keeping overall costs within budget
Delivering the software to the customer at the agreed time
Maintaining a happy and well-functioning development team
Avoiding customer complaints
2. Which of the following is not considered as a risk in project management?
Specification delays
Product competition
Testing
None of the Above
3. The process each manager follows during the life of a project is known as
Project Management
Manager life cycle
Project Management Life Cycle
Project Management Cycle
4. A 66.6% risk is considered as
Low
Nominal
Moderate
High
5. Quality planning is the process of developing a quality plan for
Practitioners
Project
Customers
Team Leader
6. Which of the following is incorrect activity for the configuration management of a software system?
Internship management
Change management
Version management
Control Management
7. Identify the sub-process of process improvement
Process introduction
Process analysis
De-process
Process distribution
8. Which of the following are the components of risk management?
Risk Assessment
Risk Control
Risk Ranking
All of the Above
9. Which of the following is a set of activities which are networked in an order and aimed towards achieving the goals of a project?
Project
Process
Project Management
All of the Above
10. Risk mitigation can be done through a variety of strategies like
Implementing controls and transferring risk
Accepting risk and Avoiding risk
All of the Above
None of the Above
11. Which of the following is correct?
Risk mitigation is an ongoing process and should be regularly reviewed and updated as the project progresses
Risk mitigation is the process of reducing the likelihood or impact of a potential risk
Project risk analysis is the process of identifying, assessing, and prioritizing potential risks to a project's success
All of the Above
12. What are the steps that can be taken when deciding to accept a risk?
Identify and assess the risk
Prioritize the risk and develop a response plan
Communicate the decision and monitor the risk
All of the Above
13. Quantitative analysis involves
Measurement of uncertainty in cost and time estimates
Probabilistic combination of individual uncertainties
Both of the Above
None of the Above
14. Normally, who is responsible for Risk Management?
Project Team
Developer
Production Team
None of the Above
15. What is the full form of RE?
Risk Expense
Risk Exposure
Risk Evaluation
None of the Above
16. Risk Exposure (RE)
17. What is risk?
Negative consequence that could occur
Negative consequence that will occur
Negative consequence that must occur
Negative consequence that shall occur
18. What assesses the risk and your plans for risk mitigation and revises these when you learn more about the risk?
Risk monitoring
Risk planning
Risk analysis
Risk identification
19. The impact of the risk will be reduced by means of which strategy?
Avoidance strategies
Minimization strategies
Contingency plans
All of the mentioned
20. Which of the following is not a risk management activity?
Risk Assessment
Risk Generation
Risk Control
All of the Above
21. ………is a systematic attempt to specify threats to the project plan?
Risk identification
Performance risk
Support risk
Risk projection
22. The primary purpose of tender is to
To select the best bid based on cost
To select the best bid based on quality
To select the best bid based on experience
All of the Above
23. The process of Tender in Nepal is governed by
Public Procurement Act, 2062
Public Procurement Act, 2063
Public Procurement Act, 2064
Public Procurement Act, 2065
24. The tender Process in Nepal typically follows
Invitation to Tender, Bid Submission, Evaluation of Bids, Award of Contract and Implementation of project
Invitation to Tender, Evaluation of Bids, Bid Submission, Award of Contract and Implementation of project
Invitation to Tender, Bid Submission, Award of Contract Evaluation of Bids, and Implementation of project
None of the Above
25. Types of Bid that are commonly used in Nepal are
Open Bid and Limited Bid
Single Source bid
Two stage bid
All of the Above
26. Which of the following office monitors the procurement process and takes necessary action to prevent any malpractice, corruption, or irregularities in the procurement process?
FCGO
PPMO
PPPO
None of these
27. In which case international level bidding is applicable in Nepal?
Where the goods or construction works as requisitioned by a Public Entity are not available under competitive price from more than one construction entrepreneur or supplier within the State of Nepal
Where no bid was submitted in response to invitation to national level bidding for the procurement
Where under an agreement entered into with a donor party, foreign goods or construction works have to be procured from foreign assistance source
All of the Above
28. A Public Entity should prepare a cost estimate of any procurement
Up to twenty five thousand rupees
Above twenty five thousand rupees
Both of the Above
None of the Above
29. The full form of EOI is
Expression of Interest
Expression of Information
Eligibility of Information
None of the Above
30. The common criteria that may include in EOI are
Eligibility and Experience
Financial Capability and Technical Capability
Mandatory documents to be submitted and the time frame for EOI submission
All of the Above
31. A Public Entity in procuring goods by selecting any method have to procure Nepali goods even if the price of the goods produced in Nepal is higher by ......percent than the foreign goods
Upto 5 percent
Upto 10 percent
Upto 20 percent
Upto 25 percent
32. To procure a consultancy service valuing more than......a Public Entity shall have to invite an expression of interest by publishing a notice
One Million
Two Million
Three Million
Four Million
33. If a consultancy service of an amount valuing more than......requires to be procured, generally an international level expression of interest
One Million
Two Million
Three Million
Four Million
34. A Public Entity shall have to procure from the individual, firm, organization or company who have obtained
Permanent Account Number
Value Added Tax registration certificate from the Inland Revenue Office
Both of the Above
None of the Above
35. A Public Entity shall have to make available pre-qualification documents to an interested individual, firm, organization or a company by charging, on the basis of the cost incurred to prepare such documents, from
One thousand to fifteen thousand Rupees
Two thousand to fifteen thousand Rupees
Three thousand to fifteen thousand Rupees
Four thousand to fifteen thousand Rupees
36. The cost estimate of a construction work of up to ......shall be specified in the notice of invitation to bid
Five million Rupees
Six million Rupees
Seven million Rupees
Eight million Rupees
37. A bidder shall have to submit along with a bid, a bid security of at least ......of the quoted amount of his/her bid in cash or the bid security issued by a commercial bank equivalent to that amount
1.5 percent
2 percent
2.5 percent
3 percent
38. Bid Validity Period For a bid or proposal of consultancy service with cost estimate of up to one hundred million Rupees
90 days
100 days
110 days
120 days
38. Bid Validity Period For a bid or proposal of consultancy service with cost estimate of up to one hundred million Rupees
90 days
100 days
110 days
120 days
39. Bid Validity Period for a bid or proposal of a consultancy service with cost estimate whatsoever above one hundred million Rupee
90 days
100 days
110 days
120 days
40. Authority to Approve the Bid Up to ten million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
41. Authority to Approve the Bid Up to thirty million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
42. Authority to Approve the Bid Up to seventy million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
43. Authority to Approve the Bid more than seventy million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
44. If a consultancy service of an amount valuing more than ______ requires to be procured, generally an international level expression of interest shall be invited.
Ten million Rupees
Twenty million Rupees
Thirty million Rupees
Forty million Rupees
45. The number of consultants to be passed on EOI at least how many consultants must be short list for further invitation to proposal
2
3
4
5
46. Provision Concerning Direct Procurement of Expendable or capital goods, or consultancy or other services or construction work valuing up to ______ may be directly procured
One hundred fifty thousand Rupees
One hundred Sixty thousand Rupees
One hundred Seventy thousand Rupees
One hundred Eighty thousand Rupees
47. A Public Entity may procure a consultancy service by concluding which of the following contracts:
Lump Sum Contract
Time-Based Contract
Performance based fee paying contract
All of the Above
48. A Public Entity shall have to procure goods, services or a construction work valuing above ______ through a bid.
One million Rupees
Two million Rupees
Three million Rupees
Four million Rupees
49. A Public Entity shall have to make available pre-qualification documents to an interested individual, firm, organization or a company by charging, on the basis of the cost incurred to prepare such documents, from ______
One thousand to Fifteen thousand Rupees
Two thousand to fifteen thousand Rupees
Three thousand to fifteen thousand Rupees
Four thousand to fifteen thousand rupees
Last updated