10.3 Project Planning and Scheduling


Project planning and scheduling are essential elements in managing a project effectively. They ensure that a project is completed on time, within budget, and meets the desired objectives. This section covers various aspects of project planning, including project classifications, project life cycle phases, planning processes, scheduling techniques, and monitoring.

1. Project Classifications

Projects can be classified in various ways, based on their duration, complexity, industry and scope. Some common classifications are:

  • Based on Complexity:

    • Simple Projects: Projects with a low degree of complexity, usually having few interdependencies and stakeholders.

    • Complex Projects: Projects involving multiple components, stakeholders, and processes, requiring more detailed planning and coordination.

  • Based on Duration:

    • Short-term Projects: Projects with a duration of less than one year.

    • Long-term Projects: Projects that span several years, often with stages or phases over time.

  • Based on Industry:

    • Construction Projects: Projects related to the building and infrastructure industry.

    • IT Projects: Software development, system upgrades, or implementation projects.

    • Manufacturing Projects: Projects focused on the production of goods or services.

  • Based on Scope:

    • Internal Projects: Projects conducted within an organization.

    • External Projects: Projects performed for clients or external stakeholders.


2. Project Life Cycle Phases

The project life cycle refers to the stages a project goes through from initiation to completion. Each phase has specific activities and milestones. The typical phases in the project life cycle are:

  1. Initiation Phase:

    • Identifying the project's objectives, scope, and stakeholders.

    • Feasibility study and securing approval or funding.

  2. Planning Phase:

    • Defining the project's detailed plan, including scope, goals, timeline, budget, and resources.

    • Risk management, quality control, and communication plans are developed.

  3. Execution Phase:

    • Actual implementation of the project plan.

    • Coordination of resources, teams, and tasks.

    • Ensuring quality control and adherence to timelines.

  4. Monitoring and Controlling Phase:

    • Continuous tracking of project progress to ensure it aligns with the plan.

    • Managing changes, risks, and issues as they arise.

    • Adjustments and corrective actions are made to stay on course.

  5. Closure Phase:

    • Finalizing all project activities, closing contracts, and releasing resources.

    • Completing project deliverables and obtaining client or stakeholder sign-off.

    • Evaluating project performance, documenting lessons learned, and archiving project records.


3. Project Planning Process

The project planning process involves outlining the steps needed to achieve the project's objectives. It includes:

  • Defining the Scope: Clarifying the work required and the project's deliverables.

  • Setting Objectives: Establishing clear and measurable goals for the project.

  • Resource Planning: Identifying the resources (personnel, equipment, materials) needed for each task.

  • Budgeting: Estimating the costs associated with each phase of the project.

  • Risk Planning: Identifying potential risks and developing mitigation strategies.

  • Time Planning: Determining the timeline, including milestones and deadlines.

  • Quality Planning: Ensuring that the project's outputs meet the required standards and expectations.

  • Communication Planning: Establishing how information will be shared among team members, stakeholders, and clients.


4. Project Scheduling Techniques

Project scheduling involves determining the timeline and sequence of project tasks. The goal is to ensure that all project activities are completed on time. Common scheduling techniques include:

  • Bar Chart (Gantt Chart)

    A Gantt chart is a visual representation of a project schedule, where tasks are shown along a timeline. It helps track progress, allocate resources, and adjust timelines.

    • Advantages: Simple, easy to understand, visually intuitive.

    • Limitations: Can be less effective for complex projects with many dependencies.

  • Critical Path Method (CPM)

    Critical Path Method (CPM) is used to determine the longest sequence of tasks (critical path) that must be completed on time to ensure the project finishes as scheduled. It helps identify the minimum project duration and highlights which tasks must be prioritized.

  • Steps:

    1. List all project tasks.

    2. Estimate the duration of each task.

    3. Identify task dependencies (which tasks must be completed before others).

    4. Calculate the critical path by determining which tasks affect the project’s duration the most.

  • Critical Path: The sequence of tasks that determines the project’s overall duration.

  • Example:

    Provided Activities:

    Activity

    Immediate Predecessors

    Duration (days)

    F

    -

    6

    G

    F

    4

    H

    F

    5

    I

    G, H

    3

    J

    G, I

    7

    Steps to Determine the Critical Path

    Activity F (No Predecessors)

    • Earliest Start (ES): 0

      • Earliest Finish (EF): 0 + 6 = 6

    Activity G (Dependent on F)

    • ES: 6 (F's EF)

    • EF: 6 + 4 = 10

    Activity H (Dependent on F)

    • ES: 6 (F's EF)

    • EF: 6 + 5 = 11

    Activity I (Dependent on G and H)

    • ES: max(10, 11) = 11 (Latest of G's EF or H's EF)

    • EF: 11 + 3 = 14

    Activity J (Dependent on G and I)

    • ES: max(10, 14) = 14 (Latest of G's EF or I's EF)

    • EF: 14 + 7 = 21

    Critical Path

    The critical path is the sequence of activities with the longest duration, as it determines the overall project duration.

    The critical path is: F → H → I → J, with a total duration: 6 + 5 + 3 + 7 = 21 days.


Program Evaluation and Review Technique (PERT)

PERT is a project management tool used to analyze and represent the tasks involved in completing a project. Unlike CPM, PERT uses probabilistic time estimates (optimistic, pessimistic, and most likely) to calculate expected durations.

Formula for expected time (te):( t_e ):

te=(to+4tm+tp)6t_e = \frac{(t_o + 4 t_m + t_p)}{6}

Where:

to = Optimistic timetm = Most likely timetp = Pessimistic timet_o \text{ = Optimistic time} \\ t_m \text{ = Most likely time} \\ t_p \text{ = Pessimistic time}

Advantages: Useful for projects with uncertain durations and complex dependencies.

Limitations: Requires accurate time estimation and can be time-consuming to develop.


5. Resource Levelling and Smoothing

Resource levelling and smoothing are techniques used to balance resource usage throughout the project to avoid over-allocation or under-utilization.

  • Resource Levelling: Adjusts the schedule (even extending the project duration if needed) to ensure resources are not over-allocated. This may lead to extending the project duration.

    • Goal: Ensure that resources are used efficiently and that no resources are overloaded.

  • Resource Smoothing: Adjusts the timing of tasks (within their available float/slack) to use resources more effectively without changing the overall project duration.

    • Goal: Even out the resource demand while maintaining the project’s timeline.

Neither resource leveling nor resource smoothing involves adding extra resources. Instead, both focus on optimizing the allocation of available resources to achieve balance or efficiency:


6. Monitoring, Evaluation, and Controlling

Once a project is underway, it is essential to monitor and evaluate progress to ensure it stays on track. The goal is to identify any deviations from the plan early and take corrective actions. Key aspects include:

  • Monitoring: Continuously tracking the project’s performance in terms of scope, time, and cost.

    • Tools used: Gantt charts, progress reports, and software tools.

  • Evaluation: Assessing the project's status and comparing actual performance against the plan.

    • Key performance indicators (KPIs) are used to evaluate the project's success.

  • Controlling: Taking corrective actions when necessary to address any issues that arise during the project.

    • Example: If a task is behind schedule, resource allocation can be adjusted, or dependencies can be reevaluated.


Conclusion

Project planning and scheduling are critical for delivering a project successfully. Properly classifying the project, defining the life cycle phases, and using effective scheduling tools like Gantt charts, CPM, and PERT ensure that the project progresses on time. Resource leveling and smoothing ensure that resources are utilized effectively. Monitoring and controlling throughout the project help maintain focus on the objectives and allow for adjustments when necessary.