MCQs On Project Planning & Scheduling
1. Which of the following is defined as a set of activities which are networked in an order and aimed toward achieving the goals?
Project
Process
Project Life Cycle
None of the Above
2. The project life cycle consists of?
Understanding the scope of the project
Formulation and planning various activities
Both A & B
Only A
3. In Project management when does planning take place?
Before the project
During the project execution
At the start of the project
After the project
4. Which of the following is the longest phase of the project management life cycle?
Initiation
Planning
Execution
Closing
5. Which of the following phases is to establish the project’s objectives, scope, and feasibility?
Initiation
Planning
Execution
Monitoring and control
6. Which of the following phases is to identify and mitigate risks, and to ensure that the project has the necessary resources and schedule?
Initiation
Planning
Execution
Monitoring and control
7. Which of the following phases is to deliver the project’s objectives within the defined scope, schedule, and budget?
Initiation
Planning
Execution
Monitoring and control
8. Which of the following is true?
The project life cycle is the sequence of phases that a project goes through from its initiation to its closure
The number and names of the phases can vary depending on the methodology used
The goal of closure phase is to complete all project-related activities, and to document the project’s results and lessons learned.
All of the Above
9. Which of the following are series of steps taken by project managers to develop a detailed plan for a project?
Define the project objectives and goals
Develop a project scope statement
Create a project schedule and plan
All of the Above
10. Feasibility study determines
Whether the project is possible with resources
Comparing the project with world class manufacturing norms
Calculate the cost crashing each unit
All of the Above
11. Different techniques that can be used for project scheduling are
Gantt charts, Critical path method (CPM)
PERT and Work breakdown structure (WBS)
Agile methodologies
All of the Above
12. Which of the following is true about Gantt chart?
A Gantt chart is a visual representation of a project schedule that shows the start and end dates of each task
It consists of a horizontal axis that represents time, and a vertical axis that lists all of the tasks that need to be completed for the project
Gantt charts are useful for project managers because they provide a clear, visual representation of the project schedule
All of the Above
13. Advantage of a Gantt Chart is
It is easy to draw
Its ability to visually represent activities and times
It depicts Project Life Cycle
All of the Above
14. Which of the following is true?
A bar chart is used to compare and show data distribution across different categories
Gantt chart is used to represent and manage the schedule of a project and its tasks
Both of the Above
None of the Above
15. Which of the following is true?
A bar chart and a Gantt chart are similar in that they both use horizontal bars to represent the duration and progress of tasks
Bar charts are useful for quickly understanding the overall progress of a project
A Gantt chart is a specialized type of bar chart that is commonly used in project management
All of the Above
16. When resources required by activities are deterministic the method used in Project Management is called
PERT
AOA
CPM
Event Management
17. Full form of PERT is
Project Evaluation and Review Technique
Project Examination and Review Technique
Project Evaluation and Risk Technique
Project Evaluation and Review Tricks
18. PERT (Project Evaluation and Review Technique) analysis is based on
Optimistic time, Pessimistic time and Most likely time
Pessimistic time, Optional time, Maximum time
Optimistic time, Efficient time, Most likely time
Minimax time, Optimistic time and harmonic time
19. Who introduced the bar charts?
Williams henry
Henry Gantt
Jane Gantt
None of the Above
20. The full form of CPM is
Critical Path Method
Control Path Method
Critical Plan Management
Control Path Management
21. In bar charts, which color is used to show the actual progress?
Red
Yellow
Blue
Green
22. Which of the following is used to represent activity in a network diagram?
Circles
Squares
Arrows
Any of the above
23. Which of the following is a project scheduling method that can be applied to software development?
PERT
CPM
CMM
Both PERT and CPM
24. A horizontal bar chart that shows project tasks against a calendar is called
Milestone
Goal
Gantt Chart
PERT Chart
25. The statistical tool that depicts a project’s tasks and the relationships between those tasks is known as
Milestone
Goal
Gantt Chart
PERT Chart
26. Which of the following are the process of project planning?
Define the project
Develop a project Plan
Identify and acquire resources
All of the Above
27. Classification of projects on the basis of as matrix, functional or projectized comes under
Organizational structure
Phase of development
Purpose
All of the above
28. Which of the following focus on day-to-day business operations and are designed to improve efficiency and productivity.
Operational projects
Tactical projects
Strategic projects
Portfolio projects
29. Which of the following address specific business needs and objectives, and are usually shorter-term in nature.
Operational projects
Tactical projects
Strategic projects
Portfolio projects
30. Which of the following align with the overall goals and mission of the organization, and are usually longer-term in nature
Operational projects
Tactical projects
Strategic projects
Portfolio projects
31. Which of the following are a collection of projects that are grouped together to achieve specific organizational objectives?
Operational projects
Tactical projects
Strategic projects
Portfolio projects
32. Which of the following is true about Resource leveling and smoothing?
Are techniques used in project management to ensure that resources are used efficiently and effectively throughout the duration of a project
Resource leveling involves adjusting the schedule of a project to ensure that resources are not over-allocated at any point in time
Resource smoothing involves making small adjustments to the schedule of a project to ensure that resources are used in a more even and consistent way over time
All of the Above
33. Which of the following are methods for resource leveling?
Manual Levelling
Software based leveling
Heuristic leveling
All of the Above
34. Heuristic leveling means
Using a set of rules or guidelines to adjust the schedule of a project
Using specialized software to automatically adjust the schedule of a project
Manually adjusting the schedule of a project
None of the Above
35. Manual leveling means
Using a set of rules or guidelines to adjust the schedule of a project
Using specialized software to automatically adjust the schedule of a project
Manually adjusting the schedule of a project
None of the Above
36. Software based leveling means
Using a set of rules or guidelines to adjust the schedule of a project
Using specialized software to automatically adjust the schedule of a project
Manually adjusting the schedule of a project
None of the Above
37. Which of the following needs to be remembered during resource leveling?
Identify critical resources and Understand resource constraints
Analyze resource allocation and Prioritize tasks
Adjust the schedule and Monitor progress
All of the Above
38. Which of the following is true?
Resource smoothing is a way to optimize the use of resources over the duration of the project
Resource leveling focuses on ensuring that resources are used efficiently throughout the project
Both techniques can be used together to improve project outcomes.
All of the Above
39. Which of the following ensure that the project stays on track and achieves its objectives?
Monitoring
Evaluation
Controlling
All of the above
40. Monitoring refers to
Process of tracking the progress of the project and comparing it to the project plan
Assessing the effectiveness of the project and determining whether it is achieving its intended objectives
The process of making adjustments to the project plan as needed to ensure that the project stays on track.
All of the Above
41. Evaluation refers to
Ongoing process of tracking the progress of the project and comparing it to the project plan
Assessing the effectiveness of the project and determining whether it is achieving its intended objectives
The process of making adjustments to the project plan as needed to ensure that the project stays on track.
All of the Above
42. Controlling refers to
Ongoing process of tracking the progress of the project and comparing it to the project plan
Assessing the effectiveness of the project and determining whether it is achieving its intended objectives
The process of making adjustments to the project plan as needed to ensure that the project stays on track.
All of the Above
43. Which of the following is not a project management goal?
Keeping overall costs within budget
Delivering the software to the customer at the agreed time
Maintaining a happy and well-functioning development team
Avoiding customer complaints
44. Which of the following is not considered as a risk in project management?
Specification delays
Product competition
Testing
None of the Above
45. The process each manager follows during the life of a project is known as
Project Management
Manager life cycle
Project Management Life Cycle
Project Management Cycle
46. A 66.6% risk is considered as
Low
Nominal
Moderate
High
47. Quality planning is the process of developing a quality plan for
Practitioners
Project
Customers
Team Leader
48. Which of the following is incorrect activity for the configuration management of a software system?
Internship management
Change management
Version management
Control Management
49. Identify the sub-process of process improvement
Process introduction
Process analysis
De-process
Process distribution
50. Which of the following are the components of risk management?
Risk Assessment
Risk Control
Risk Ranking
All of the above
51. Which of the following is a set of activities which are networked in an order and aimed towards achieving the goals of a project?
Project
Process
Project Management
All of the Above
52. Risk mitigation can be done through a variety of strategies like
Implementing controls and transferring risk
Accepting risk and avoiding risk
All of the Above
None of the Above
53. Which of the following is correct?
Risk mitigation is an ongoing process and should be regularly reviewed and updated as the project progresses
Risk mitigation is the process of reducing the likelihood or impact of a potential risk
Project risk analysis is the process of identifying, assessing, and prioritizing potential risks to a project's success
All of the Above
54. What are the steps that can be taken when deciding to accept a risk?
Identify and assess the risk
Prioritize the risk and develop a response plan
Communicate the decision and monitor the risk
All of the Above
55. Quantitative analysis involves
Measurement of uncertainty in cost and time estimates
Probabilistic combination of individual uncertainties
Both of the Above
None of the Above
56. Normally, who is responsible for Risk Management?
Project Team
Developer
Production Team
None of the Above
57. What is the full form of RE?
Risk Expense
Risk Exposure
Risk Evaluation
None of the Above
58. Risk Exposure (RE)
RE = Probability * Impact
RE = 0.1 * Probability - Impact
RE = Probability / Impact
RE = Impact
59. What is risk?
Negative consequence that could occur
Negative consequence that will occur
Negative consequence that must occur
Negative consequence that shall occur
60. What assesses the risk and your plans for risk mitigation and revises these when you learn more about the risk?
Risk monitoring
Risk planning
Risk analysis
Risk identification
61. The impact of the risk will be reduced by means of which strategy?
Avoidance strategies
Minimization strategies
Contingency plans
All of the mentioned
62. Which of the following is not a risk management activity?
Risk Assessment
Risk Generation
Risk Control
All of the Above
63. ______ is a systematic attempt to specify threats to the project plan?
Risk identification
Performance risk
Support risk
Risk projection
64. The primary purpose of tender is to
To select the best bid based on cost
To select the best bid based on quality
To select the best bid based on experience
All of the Above
65. The process of Tender in Nepal is governed by
Public Procurement Act, 2062
Public Procurement Act, 2063
Public Procurement Act, 2064
Public Procurement Act, 2065
66. The tender Process in Nepal typically follows
Invitation to Tender, Bid Submission, Evaluation of Bids, Award of Contract and Implementation of project
Invitation to Tender, Evaluation of Bids, Bid Submission, Award of Contract and Implementation of project
Invitation to Tender, Bid Submission, Award of Contract Evaluation of Bids, and Implementation of project
None of the Above
67. Types of Bid that are commonly used in Nepal are
Open Bid and Limited Bid
Single Source bid
Two stage bid
All of the Above
68. Which of the following office monitors the procurement process and takes necessary action to prevent any malpractice, corruption, or irregularities in the procurement process?
FCGO
PPMO
PPPO
None of these
69. In which case international level bidding is applicable in Nepal?
Where the goods or construction works as requisitioned by a Public Entity are not available under competitive price from more than one construction entrepreneur or supplier within the State of Nepal
Where no bid was submitted in response to invitation to national level bidding for the procurement
Where under an agreement entered into with a donor party, foreign goods or construction works have to be procured from foreign assistance source
All of the Above
70. A Public Entity should prepare a cost estimate of any procurement
Up to twenty five thousand rupees
Above twenty five thousand rupees
Both of the Above
None of the Above
71. The full form of EOI is
Expression of Interest
Expression of Information
Eligibility of Information
None of the Above
72. The common criteria that may include in EOI are
Eligibility and Experience
Financial Capability and Technical Capability
Mandatory documents to be submitted and the time frame for EOI submission
All of the Above
73. A Public Entity in procuring goods by selecting any method have to procure Nepali goods even if the price of the goods produced in Nepal is higher by ......percent than the foreign goods
Upto 5 percent
Upto 10 percent
Upto 20 percent
Upto 25 percent
74. To procure a consultancy service valuing more than......a Public Entity shall have to invite a expression of interest by publishing a notice
One Million
Two Million
Three Million
Four Million
75. If a consultancy service of an amount valuing more than......requires to be procured, generally an international level expression of interest
One Million
Two Million
Three Million
Four Million
76. A Public Entity shall have to procure from the individual, firm, organization or company who have obtained
Permanent Account Number
Value Added Tax registration certificate from the Inland Revenue Office
Both of the Above
None of the Above
77. A Public Entity shall have to make available pre-qualification documents to an interested individual, firm, organization or a company by charging, on the basis of the cost incurred to prepare such documents, from
One thousand to fifteen thousand Rupees.
Two thousand to fifteen thousand Rupees.
Three thousand to fifteen thousand Rupees.
Four thousand to fifteen thousand Rupees.
78. The cost estimate of a construction work of up to ...... shall be specified in the notice of invitation to bid.
Five million Rupees
Six million Rupees
Seven million Rupees
Eight million Rupees
79. A bidder shall have to submit along with a bid, a bid security of at least ...... of the quoted amount of his/her bid in cash or the bid security issued by a commercial bank equivalent to that amount
1.5 percent
2 percent
2.5 percent
3 percent
80. Bid Validity Period For a bid or proposal of consultancy service with cost estimate of up to one hundred million Rupees
90 days
100 days
110 days
120 days
81. Bid Validity Period for a bid or proposal of a consultancy service with cost estimate whatsoever above one hundred million Rupee
90 days
100 days
110 days
120 days
82. Authority to Approve the Bid Up to ten million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
83. Authority to Approve the Bid Up to thirty million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
84. Authority to Approve the Bid Up to seventy million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
85. Authority to Approve the Bid more than seventy million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
86. If a consultancy service of an amount valuing more than ...... requires to be procured, generally an international level expression of interest shall be invited.
Ten million Rupees
Twenty million Rupees
Thirty million Rupees
Forty million Rupees
87. The number of consultants to be passed on EOI at least how many consultants must be short list for further invitation to proposal
2
3
4
5
88. Provision Concerning Direct Procurement of Expendable or capital goods, or consultancy or other services or construction work valuing up to ...... may be directly procured
One hundred fifty thousand Rupees
One hundred Sixty thousand Rupees
One hundred Seventy thousand Rupees
One hundred Eighty thousand Rupees
Last updated