1. Which of the following is not a project management goal?
Keeping overall costs within budget
Delivering the software to the customer at the agreed time
Maintaining a happy and well-functioning development team
Avoiding customer complaints
Show me the answer
Answer: 4. Avoiding customer complaints
Explanation:
The primary goals of project management include keeping costs within budget, delivering projects on time, and maintaining a well-functioning team.
Avoiding customer complaints is not a direct goal of project management, although it may be a byproduct of successful project management.
The other options are core objectives of project management.
2. Which of the following is not considered as a risk in project management?
Specification delays
Product competition
Testing
None of the Above
Show me the answer
Answer: 3. Testing
Explanation:
Risks in project management typically include delays, competition, and resource constraints.
Testing is a standard part of the project lifecycle and is not considered a risk.
The other options are common risks that project managers must address.
3. The process each manager follows during the life of a project is known as
Project Management
Manager life cycle
Project Management Life Cycle
Project Management Cycle
Show me the answer
Answer: 3. Project Management Life Cycle
Explanation:
The Project Management Life Cycle (PMLC) refers to the phases a project goes through from initiation to closure.
It includes planning, execution, monitoring, and closing phases.
The other options are not standard terms used to describe this process.
4. A 66.6% risk is considered as
Low
Nominal
Moderate
High
Show me the answer
Answer: 4. High
Explanation:
A risk probability of 66.6% is considered high in project management.
High-risk probabilities require significant attention and mitigation strategies.
The other options describe lower levels of risk.
5. Quality planning is the process of developing a quality plan for
Practitioners
Project
Customers
Team Leader
Show me the answer
Answer: 2. Project
Explanation:
Quality planning involves creating a plan to ensure that the project meets its quality objectives.
It focuses on the project's deliverables and processes, not on individual practitioners or customers.
The other options are not the primary focus of quality planning.
6. Which of the following is incorrect activity for the configuration management of a software system?
Internship management
Change management
Version management
Control Management
Show me the answer
Answer: 1. Internship management
Explanation:
Configuration management involves managing changes, versions, and control of software systems.
Internship management is unrelated to configuration management and is not a standard activity in this context.
The other options are core activities of configuration management.
7. Identify the sub-process of process improvement
Process introduction
Process analysis
De-process
Process distribution
Show me the answer
Answer: 2. Process analysis
Explanation:
Process improvement involves analyzing existing processes to identify areas for improvement.
Process analysis is a key sub-process in this context.
The other options are not standard sub-processes of process improvement.
8. Which of the following are the components of risk management?
Risk Assessment
Risk Control
Risk Ranking
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
Risk management includes risk assessment, control, and ranking.
These components help identify, evaluate, and mitigate risks in a project.
All the options are essential parts of risk management.
9. Which of the following is a set of activities which are networked in an order and aimed towards achieving the goals of a project?
Project
Process
Project Management
All of the Above
Show me the answer
Answer: 1. Project
Explanation:
A project is a set of activities that are organized in a sequence to achieve specific goals.
Process and project management are broader concepts that include managing and executing projects.
The correct answer is "Project."
10. Risk mitigation can be done through a variety of strategies like
Implementing controls and transferring risk
Accepting risk and Avoiding risk
All of the Above
None of the Above
Show me the answer
Answer: 3. All of the Above
Explanation:
Risk mitigation strategies include implementing controls, transferring risk, accepting risk, and avoiding risk.
These strategies help reduce the impact or likelihood of risks in a project.
All the options are valid risk mitigation strategies.
11. Which of the following is correct?
Risk mitigation is an ongoing process and should be regularly reviewed and updated as the project progresses
Risk mitigation is the process of reducing the likelihood or impact of a potential risk
Project risk analysis is the process of identifying, assessing, and prioritizing potential risks to a project's success
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
Risk mitigation is indeed an ongoing process that requires regular review and updates.
It involves reducing the likelihood or impact of risks.
Project risk analysis includes identifying, assessing, and prioritizing risks.
All the statements are correct and interrelated.
12. What are the steps that can be taken when deciding to accept a risk?
Identify and assess the risk
Prioritize the risk and develop a response plan
Communicate the decision and monitor the risk
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
When deciding to accept a risk, the steps include identifying and assessing the risk, prioritizing it, developing a response plan, communicating the decision, and monitoring the risk.
All these steps are essential for effective risk management.
Therefore, all the options are correct.
13. Quantitative analysis involves
Measurement of uncertainty in cost and time estimates
Probabilistic combination of individual uncertainties
Both of the Above
None of the Above
Show me the answer
Answer: 3. Both of the Above
Explanation:
Quantitative analysis in project management involves measuring uncertainties in cost and time estimates.
It also includes combining individual uncertainties probabilistically to assess overall project risk.
Both options are correct and describe key aspects of quantitative analysis.
14. Normally, who is responsible for Risk Management?
Project Team
Developer
Production Team
None of the Above
Show me the answer
Answer: 1. Project Team
Explanation:
Risk management is typically the responsibility of the project team.
The project team identifies, assesses, and mitigates risks throughout the project lifecycle.
Developers and production teams may contribute, but the primary responsibility lies with the project team.
15. What is the full form of RE?
Risk Expense
Risk Exposure
Risk Evaluation
None of the Above
Show me the answer
Answer: 2. Risk Exposure
Explanation:
RE stands for Risk Exposure, which is a measure of the potential impact of a risk on a project.
It is calculated as the product of the probability of the risk occurring and its potential impact.
The other options are not correct expansions of RE.
16. Risk Exposure (RE)
RE=Probability×Impact
RE=0.1×Probability−Impact
RE=ImpactProbability
RE=Impact
Show me the answer
Answer: 1. RE=Probability×Impact
Explanation:
Risk Exposure (RE) is calculated by multiplying the probability of a risk occurring by its potential impact.
This formula helps quantify the potential effect of a risk on the project.
The other options are incorrect representations of RE.
17. What is risk?
Negative consequence that could occur
Negative consequence that will occur
Negative consequence that must occur
Negative consequence that shall occur
Show me the answer
Answer: 1. Negative consequence that could occur
Explanation:
Risk refers to the possibility of a negative consequence occurring in the future.
It is not certain that the consequence will occur, but there is a possibility.
The other options imply certainty, which is not the nature of risk.
18. What assesses the risk and your plans for risk mitigation and revises these when you learn more about the risk?
Risk monitoring
Risk planning
Risk analysis
Risk identification
Show me the answer
Answer: 1. Risk monitoring
Explanation:
Risk monitoring involves continuously assessing risks and updating mitigation plans as new information becomes available.
It ensures that the project team remains aware of potential risks and can respond effectively.
The other options are part of the risk management process but do not specifically involve ongoing assessment and revision.
19. The impact of the risk will be reduced by means of which strategy?
Avoidance strategies
Minimization strategies
Contingency plans
All of the mentioned
Show me the answer
Answer: 4. All of the mentioned
Explanation:
Risk impact can be reduced through avoidance strategies, minimization strategies, and contingency plans.
Each strategy plays a role in mitigating the effects of risks on the project.
Therefore, all the options are correct.
20. Which of the following is not a risk management activity?
Risk Assessment
Risk Generation
Risk Control
All of the Above
Show me the answer
Answer: 2. Risk Generation
Explanation:
Risk management activities include risk assessment, control, and monitoring.
Risk generation is not a standard activity in risk management; risks are identified, not generated.
The other options are core activities of risk management.
21. ………is a systematic attempt to specify threats to the project plan?
Risk identification
Performance risk
Support risk
Risk projection
Show me the answer
Answer: 1. Risk identification
Explanation:
Risk identification is the process of systematically identifying potential threats to the project plan.
It is the first step in the risk management process.
The other options describe specific types of risks or risk-related activities.
22. The primary purpose of tender is to
To select the best bid based on cost
To select the best bid based on quality
To select the best bid based on experience
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
The primary purpose of a tender is to select the best bid based on cost, quality, and experience.
These factors ensure that the selected bidder can deliver the project effectively.
Therefore, all the options are correct.
23. The process of Tender in Nepal is governed by
Public Procurement Act, 2062
Public Procurement Act, 2063
Public Procurement Act, 2064
Public Procurement Act, 2065
Show me the answer
Answer: 2. Public Procurement Act, 2063
Explanation:
The tender process in Nepal is governed by the Public Procurement Act, 2063.
This act outlines the procedures and regulations for public procurement.
The other options are incorrect years for the act.
24. The tender Process in Nepal typically follows
Invitation to Tender, Bid Submission, Evaluation of Bids, Award of Contract and Implementation of project
Invitation to Tender, Evaluation of Bids, Bid Submission, Award of Contract and Implementation of project
Invitation to Tender, Bid Submission, Award of Contract Evaluation of Bids, and Implementation of project
None of the Above
Show me the answer
Answer: 1. Invitation to Tender, Bid Submission, Evaluation of Bids, Award of Contract and Implementation of project
Explanation:
The tender process in Nepal follows a sequence of steps: invitation to tender, bid submission, evaluation of bids, award of contract, and project implementation.
This sequence ensures a fair and transparent procurement process.
The other options do not follow the correct sequence.
25. Types of Bid that are commonly used in Nepal are
Open Bid and Limited Bid
Single Source bid
Two stage bid
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
Common types of bids used in Nepal include open bids, limited bids, single-source bids, and two-stage bids.
These bidding methods cater to different procurement needs and scenarios.
Therefore, all the options are correct.
26. Which of the following office monitors the procurement process and takes necessary action to prevent any malpractice, corruption, or irregularities in the procurement process?
FCGO
PPMO
PPPO
None of these
Show me the answer
Answer: 2. PPMO
Explanation:
The Public Procurement Monitoring Office (PPMO) is responsible for monitoring the procurement process in Nepal.
It ensures that procurement activities are conducted transparently and without corruption.
The other options are not relevant to procurement monitoring.
27. In which case international level bidding is applicable in Nepal?
Where the goods or construction works as requisitioned by a Public Entity are not available under competitive price from more than one construction entrepreneur or supplier within the State of Nepal
Where no bid was submitted in response to invitation to national level bidding for the procurement
Where under an agreement entered into with a donor party, foreign goods or construction works have to be procured from foreign assistance source
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
International level bidding in Nepal is applicable in cases where goods or services are not available domestically, no bids are received in national bidding, or foreign assistance is required.
These scenarios justify the need for international bidding.
Therefore, all the options are correct.
28. A Public Entity should prepare a cost estimate of any procurement
Up to twenty five thousand rupees
Above twenty five thousand rupees
Both of the Above
None of the Above
Show me the answer
Answer: 2. Above twenty five thousand rupees
Explanation:
A Public Entity in Nepal is required to prepare a cost estimate for procurement above twenty-five thousand rupees.
This ensures transparency and accountability in the procurement process.
The other options are not correct thresholds for cost estimation.
29. The full form of EOI is
Expression of Interest
Expression of Information
Eligibility of Information
None of the Above
Show me the answer
Answer: 1. Expression of Interest
Explanation:
EOI stands for Expression of Interest, which is a document submitted by potential bidders to indicate their interest in a project.
It is commonly used in the procurement process to shortlist qualified bidders.
The other options are incorrect expansions of EOI.
30. The common criteria that may include in EOI are
Eligibility and Experience
Financial Capability and Technical Capability
Mandatory documents to be submitted and the time frame for EOI submission
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
The criteria for an Expression of Interest (EOI) typically include eligibility, experience, financial capability, technical capability, mandatory documents, and submission timelines.
These criteria help ensure that only qualified bidders are considered.
Therefore, all the options are correct.
31. A Public Entity in procuring goods by selecting any method have to procure Nepali goods even if the price of the goods produced in Nepal is higher by ......percent than the foreign goods
Upto 5 percent
Upto 10 percent
Upto 20 percent
Upto 25 percent
Show me the answer
Answer: 2. Upto 10 percent
Explanation:
Public Entities in Nepal are required to prioritize Nepali goods even if they are up to 10% more expensive than foreign goods.
This policy supports local industries and promotes economic growth.
The other options are incorrect percentages.
32. To procure a consultancy service valuing more than......a Public Entity shall have to invite an expression of interest by publishing a notice
One Million
Two Million
Three Million
Four Million
Show me the answer
Answer: 1. One Million
Explanation:
For consultancy services valued at more than one million rupees, a Public Entity must invite an Expression of Interest (EOI) by publishing a notice.
This ensures transparency and competition in the procurement process.
The other options are incorrect thresholds.
33. If a consultancy service of an amount valuing more than......requires to be procured, generally an international level expression of interest
One Million
Two Million
Three Million
Four Million
Show me the answer
Answer: 3. Three Million
Explanation:
For consultancy services valued at more than three million rupees, an international level Expression of Interest (EOI) is generally required.
This ensures that the best expertise is available for high-value projects.
The other options are incorrect thresholds.
34. A Public Entity shall have to procure from the individual, firm, organization or company who have obtained
Permanent Account Number
Value Added Tax registration certificate from the Inland Revenue Office
Both of the Above
None of the Above
Show me the answer
Answer: 3. Both of the Above
Explanation:
Public Entities in Nepal are required to procure goods and services from entities that have a Permanent Account Number (PAN) and a Value Added Tax (VAT) registration certificate.
These requirements ensure compliance with tax regulations.
Therefore, both options are correct.
35. A Public Entity shall have to make available pre-qualification documents to an interested individual, firm, organization or a company by charging, on the basis of the cost incurred to prepare such documents, from
One thousand to fifteen thousand Rupees
Two thousand to fifteen thousand Rupees
Three thousand to fifteen thousand Rupees
Four thousand to fifteen thousand Rupees
Show me the answer
Answer: 1. One thousand to fifteen thousand Rupees
Explanation:
Public Entities in Nepal charge between one thousand and fifteen thousand rupees for pre-qualification documents, based on the cost of preparation.
This fee ensures that only serious bidders access the documents.
The other options are incorrect fee ranges.
36. The cost estimate of a construction work of up to ......shall be specified in the notice of invitation to bid
Five million Rupees
Six million Rupees
Seven million Rupees
Eight million Rupees
Show me the answer
Answer: 2. Six million Rupees
Explanation:
For construction works valued up to six million rupees, the cost estimate must be specified in the notice of invitation to bid.
This ensures transparency and helps bidders prepare accurate proposals.
The other options are incorrect thresholds.
37. A bidder shall have to submit along with a bid, a bid security of at least ......of the quoted amount of his/her bid in cash or the bid security issued by a commercial bank equivalent to that amount
1.5 percent
2 percent
2.5 percent
3 percent
Show me the answer
Answer: 3. 2.5 percent
Explanation:
Bidders in Nepal are required to submit a bid security of at least 2.5% of the quoted amount.
This ensures that bidders are committed to their proposals.
The other options are incorrect percentages.
38. Bid Validity Period For a bid or proposal of consultancy service with cost estimate of up to one hundred million Rupees
90 days
100 days
110 days
120 days
Show me the answer
Answer: 1. 90 days
Explanation:
The bid validity period for consultancy services valued up to one hundred million rupees is 90 days.
This ensures that bids remain
38. Bid Validity Period For a bid or proposal of consultancy service with cost estimate of up to one hundred million Rupees
90 days
100 days
110 days
120 days
Show me the answer
Answer: 1. 90 days
Explanation:
The bid validity period for consultancy services with a cost estimate of up to one hundred million Rupees is typically 90 days.
This ensures that the bid remains valid for a reasonable period while the evaluation process is completed.
The other options are not standard for this cost estimate.
39. Bid Validity Period for a bid or proposal of a consultancy service with cost estimate whatsoever above one hundred million Rupee
90 days
100 days
110 days
120 days
Show me the answer
Answer: 4. 120 days
Explanation:
For consultancy services with a cost estimate above one hundred million Rupees, the bid validity period is typically 120 days.
This extended period allows for more complex evaluations and decision-making processes.
The other options are not standard for this cost estimate.
40. Authority to Approve the Bid Up to ten million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
Show me the answer
Answer: 1. Chief of the Office of Gazetted Third Class
Explanation:
For bids up to ten million Rupees, the authority to approve lies with the Chief of the Office of Gazetted Third Class.
This ensures that smaller bids are handled efficiently at the appropriate administrative level.
The other options are not responsible for this level of approval.
41. Authority to Approve the Bid Up to thirty million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
Show me the answer
Answer: 2. Chief of the Office of Gazetted Second Class
Explanation:
For bids up to thirty million Rupees, the authority to approve lies with the Chief of the Office of Gazetted Second Class.
This ensures that bids of this size are handled by a higher administrative level.
The other options are not responsible for this level of approval.
42. Authority to Approve the Bid Up to seventy million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
Show me the answer
Answer: 3. Chief of the Office of Gazetted First Class
Explanation:
For bids up to seventy million Rupees, the authority to approve lies with the Chief of the Office of Gazetted First Class.
This ensures that larger bids are handled by a senior administrative level.
The other options are not responsible for this level of approval.
43. Authority to Approve the Bid more than seventy million Rupees
Chief of the Office of Gazetted Third Class
Chief of the Office of Gazetted Second Class
Chief of the Office of Gazetted First Class
Chief of Department
Show me the answer
Answer: 4. Chief of Department
Explanation:
For bids exceeding seventy million Rupees, the authority to approve lies with the Chief of Department.
This ensures that the largest bids are handled by the highest administrative level.
The other options are not responsible for this level of approval.
44. If a consultancy service of an amount valuing more than ______ requires to be procured, generally an international level expression of interest shall be invited.
Ten million Rupees
Twenty million Rupees
Thirty million Rupees
Forty million Rupees
Show me the answer
Answer: 3. Thirty million Rupees
Explanation:
For consultancy services valuing more than thirty million Rupees, an international level expression of interest is typically required.
This ensures that the procurement process attracts global expertise and competition.
The other options are not standard thresholds for international procurement.
45. The number of consultants to be passed on EOI at least how many consultants must be short list for further invitation to proposal
2
3
4
5
Show me the answer
Answer: 2. 3
Explanation:
At least three consultants must be shortlisted from the Expression of Interest (EOI) for further invitation to submit proposals.
This ensures a competitive and fair selection process.
The other options do not meet the minimum requirement.
46. Provision Concerning Direct Procurement of Expendable or capital goods, or consultancy or other services or construction work valuing up to ______ may be directly procured
One hundred fifty thousand Rupees
One hundred Sixty thousand Rupees
One hundred Seventy thousand Rupees
One hundred Eighty thousand Rupees
Show me the answer
Answer: 1. One hundred fifty thousand Rupees
Explanation:
Direct procurement is allowed for goods, services, or construction work valuing up to one hundred fifty thousand Rupees.
This simplifies the procurement process for smaller-value items.
The other options exceed the threshold for direct procurement.
47. A Public Entity may procure a consultancy service by concluding which of the following contracts:
Lump Sum Contract
Time-Based Contract
Performance based fee paying contract
All of the Above
Show me the answer
Answer: 4. All of the Above
Explanation:
Public entities can procure consultancy services through various contract types, including lump sum, time-based, and performance-based fee-paying contracts.
This flexibility allows for tailored agreements based on the nature of the consultancy.
All the options are valid contract types.
48. A Public Entity shall have to procure goods, services or a construction work valuing above ______ through a bid.
One million Rupees
Two million Rupees
Three million Rupees
Four million Rupees
Show me the answer
Answer: 1. One million Rupees
Explanation:
For goods, services, or construction work valuing above one million Rupees, a public entity must use a bidding process.
This ensures transparency and competition in procurement.
The other options are not the standard threshold for mandatory bidding.
49. A Public Entity shall have to make available pre-qualification documents to an interested individual, firm, organization or a company by charging, on the basis of the cost incurred to prepare such documents, from ______
One thousand to Fifteen thousand Rupees
Two thousand to fifteen thousand Rupees
Three thousand to fifteen thousand Rupees
Four thousand to fifteen thousand rupees
Show me the answer
Answer: 1. One thousand to Fifteen thousand Rupees
Explanation:
Public entities charge between one thousand to fifteen thousand Rupees for pre-qualification documents, based on the cost of preparation.
This fee ensures that the documents are accessible while covering administrative costs.